Guide
Auction Fees and the Buyer's Premium:
What You Pay Before Completion
The hammer price is not the bill. On top of it come the auctioneer's own fee where the terms set one, your legal costs, stamp duty land tax where it applies, and the cost of any loan.
Written by Justin, Principal · Updated
Our guides are researched and drafted with digital tools, then written and approved by Justin, Principal, from his own experience.
The short answer. Up to four costs can sit on top of the hammer price: the auctioneer's fee, legal costs, stamp duty land tax and finance. The deposit is paid straight after the auction, by the auctioneer's deadline. Where the legal pack sets no other date, completion is due 20 business days after the contract date.
Each payment around the hammer price has its own clock
Auction fees in the UK are set by each auctioneer, so we list the types, not a market rate. We print a figure only where a published source gives one, as a single example.
| Payment | What it is | When it falls due | Example figure |
|---|---|---|---|
| Deposit | The greater of the auctioneer's stated minimum and 10% of the price. Held until completion | Straight after the auction, by the auctioneer's deadline | One auctioneer's terms: minimum £5,000, paid by 15:30 the next day |
| Buyer's premium or administration fee | The auctioneer's own charge. Payable only if the special conditions or the auctioneer's extra conditions say so | As the auctioneer's terms say | One auctioneer's published fee sheet, read 3 November 2026: £1,800 including VAT on purchases of £20,000 and over |
| Legal pack, searches, your solicitor | The seller supplies the pack. Your solicitor reads it and runs searches | Before you bid, then to completion | Ask your solicitor for a quote |
| Stamp duty land tax | Tax on the purchase | Within 14 days of the effective date of the transaction | See the GOV.UK table below |
| Finance costs | Interest, our fee, the lender's legal fees and valuation | Interest monthly or rolled up; our fee on completion; ask the lender about the rest | See the worked sum |
The Conditions do not set a buyer's premium, and neither copy we read gives a rate. The charge comes from the auctioneer's terms, so find it before you register to bid.
The Conditions fix the deposit and the clock, and the legal pack can change them
The RICS Common Auction Conditions, Edition 5.0, set the deposit at the greater of the auctioneer's minimum and 10% of the price. The time to pay is the auctioneer's, so read your auctioneer's own deadline.
Where the auction uses the Conditions and the legal pack sets no other date, completion is due 20 business days after the contract date. The contract date is normally auction day, so that is about four weeks from the hammer, a little longer with bank holidays.
Miss the date and the buyer pays the seller interest on the money owed, counted from the agreed completion date. After a notice to complete, the seller can usually keep the deposit and claim its losses.
We found no 10 minute or 3 minute rule in the RICS Conditions
People search for the 10 minute rule and the 3 minute rule at auction. The Conditions contain neither. We searched the Edition 5.0 text in two auctioneers' published copies and found no such rule.
We could not find a source that explains either phrase, so we will not guess. If an auctioneer quotes a time limit, it will sit in that auctioneer's own terms or the lot's special conditions. Ask for it in writing before the sale.
Stamp duty is a tax with its own 14 day clock
You file the return and pay the tax within 14 days of the effective date of the transaction. A solicitor or conveyancer can send the return for you.
Companies pay the higher rates on a residential purchase of £40,000 or more, with exceptions. GOV.UK says an individual usually pays them when they own another residential property.
The higher rates from 1 April 2025 (GOV.UK, read 3 November 2026):
| Part of the price | Rate |
|---|---|
| Up to £125,000 | 5% |
| £125,001 to £250,000 | 7% |
| £250,001 to £925,000 | 10% |
| £925,001 to £1.5 million | 15% |
| Above £1.5 million | 17% |
GOV.UK also lists a 2% surcharge for non UK residents and other rates for non residential property. Check your own case in the GOV.UK calculator or with your solicitor.
A £300,000 lot, from hammer to completion
This is an illustration, not a client. The price, the premium, the loan share and the term are assumptions. A company buys a plain residential investment house, so the higher stamp duty rates apply. Interest is rolled up and paid on repayment. The loan is sized on the lower of the price and the valuation, and the valuer agrees the price.
| Line | Working | Amount |
|---|---|---|
| Hammer price (assumed) | £300,000 | |
| Deposit, due by the auctioneer's deadline | 10% of £300,000 | £30,000 |
| Buyer's premium, due as the auctioneer's terms say (assumed) | 2% = £6,000, plus 20% VAT £1,200 | £7,200 |
| Bridging loan (assumed) | 70% of the price | £210,000 |
| Balance of the price, due on completion | £300,000 less £30,000 less £210,000 | £60,000 |
| Our fee, due on completion | 1% of £210,000. Our fee: generally 1% of the gross loan, due on completion. On a complex case an application fee can apply, agreed in writing first | £2,100 |
| Stamp duty land tax, due within 14 days of the effective date | £6,250 + £8,750 + £5,000 | £20,000 |
| Your own money in total | £30,000 + £7,200 + £60,000 + £2,100 + £20,000 | £119,300 |
| Interest | £210,000 at 0.76% a month (43 lenders, as at 20 November 2026) is £1,596 a month, for 6 months | £9,576 |
| Lender's legal fees | About £1,500 to £2,000 plus VAT on a loan of around £200k; more on a larger loan | Quote needed |
| Your own solicitor | Charged by your own solicitor; ask for a quote | Quote needed |
| Valuation | Nil to about £100 for a desktop valuation; up to about £2,000 for a full one, plus VAT | Quote needed |
| Lender's arrangement fee | Set by the lender, so ask for the figure early | Quote needed |
Illustrative: every case is priced individually.
The premium, stamp duty, our fee and six months of interest come to about £39,000, roughly 13% of the hammer price, on these assumptions, before legal and valuation costs.
If the room pushes the hammer well above the guide, see what that does to the bridge.
Add every line before you set your top bid, not after. In the sum above a £300,000 lot asks for about £119,000 of your own money on these assumptions, before interest and third party fees.
The bid is the one number you choose. The tax and the clock are set by others. Ask for the premium first, because it sits in the auctioneer's terms, not in the Conditions.
Questions we hear about auction costs
Can a bridging loan pay the deposit?
Is VAT added to the hammer price?
Do I pay stamp duty on the day of the sale?
Who provides the legal pack?
Buying at auction and want to know how much of the cost a bridge can cover? Send us the lot, the date of the sale and your way out. Indicative terms within 4 hours on straightforward deals, often quicker.
Discuss your deal 0330 223 7872
Run your own sums in the calculator.
For business or investment purposes only - never secured on a home you or your family live in.
Sources
- RICS Common Auction Conditions, Edition 5.0, read in two auctioneers' published copies (February 2026), 3 November 2026; RICS's own copy was not read.
- GOV.UK, Higher rates of Stamp Duty Land Tax (last updated 1 April 2025).
- GOV.UK, Stamp Duty Land Tax online and paper returns (published 26 June 2026). Both read 3 November 2026.
- One auctioneer's published fee sheet (undated), read 3 November 2026.
- RICS, property auctions consumer guide (5 June 2024), read 3 November 2026.
Related Finance
Ready to Discuss Your Deal?
No obligation. We'll tell you what's possible and what it'll cost. We read every enquiry the same working day and usually reply by phone, often within a couple of hours.