Land & Planning
Planning Delays: Borrowing Around a Late Decision
Published 3 March 2026
In the spring quarter of 2026, only 19 in every 100 major planning applications in England were decided inside the statutory 13 weeks. Yet 91 in every 100 were decided "on time". Both figures are true, and the gap between them is the whole story of planning delay: the deadline is usually moved by agreement, and your bridging loan has not agreed to move with it.
The short answer. If you buy land with planning pending, plan for the decision to arrive later than the statutory date, and write that into the loan: a term that covers a late decision plus the time to exit, an extension price agreed up front, and a plan B if the answer is no. Each extra month on the example below costs about £5,088 in interest. Knowing that number before you sign is cheaper than learning it afterwards. We arrange land bridging loans for business and investment purposes, from £200k.
Discuss your deal 0330 223 7872
What the Official Numbers Say
The government publishes planning decision statistics every quarter. The newest set, updated on 29 October 2026, covers April to June 2026. Four lines in it matter to anyone buying land.
- Major applications: 91% decided within 13 weeks or the agreed time, unchanged on a year earlier. Just 19% were decided inside the statutory 13 weeks, 4 percentage points fewer than a year before.
- Minor applications: 87% inside 8 weeks or the agreed time, and 39% inside the statutory 8 weeks.
- How the time gets agreed: 77% of major decisions came with a performance agreement, the label that covers extensions of time, planning performance agreements and environmental impact assessments. Where one existed, 93% of major decisions were made on time against its terms, compared with 84% without one.
- The good news: councils granted 88% of the decisions in the quarter, unchanged on the year.
Most applications are approved. The cost is rarely a refusal. It is the extra months before the approval arrives. The statistics give no average number of days for a major decision, so we will not invent one. What they do show is that for a major scheme the statutory date is closer to a starting gun than a finish line.
Source: Ministry of Housing, Communities and Local Government, Planning applications in England: April to June 2026. The next set is scheduled for December 2026.
What Has Changed in the Law, and What Has Not?
The Planning and Infrastructure Act 2025 is being switched on in stages. The law firm Herbert Smith Freehills Kramer set out where things stood in a June 2026 briefing. Judicial review extensions, compulsory purchase reforms and development corporation powers had been in force since 18 February 2026. Planning fees and the national scheme of delegation for planning committees were still waiting on regulations. A further commencement order, made on 16 June 2026, sets three more dates: 24 July, 1 September and 31 October 2026. Which sections each date brings in, our sources did not say, and we are not going to guess. Watch item, not a promise: the stated aim is faster, more predictable decisions, and the figures above are the test of that.
One change is already visible for housing sites in nutrient-sensitive catchments. On 17 September 2026 Natural England put out the first draft Environmental Delivery Plan and took comments on it until 27 October 2026. The plan is for the Norfolk Broads and River Wensum catchments. In place of site-by-site mitigation it proposes a levy of £2,675 a home, before indexation and VAT (Burges Salmon briefing, 22 September 2026). A draft, then, and for one corner of England. Anywhere else with a nutrient problem, your planning consultant should tell you which route applies and how long it adds. That question belongs before you complete, not after.
What Does a Month of Delay Cost?
Take a made-up company and a real set of numbers. The plot costs £800,000. The application for a block of flats is about to be validated. The company borrows £480,000, which is 60% of the price, for 12 months, with the interest rolled up. Repayment comes from selling the site with consent, or from a refinance once permission lands.
The rate in the sums is the published average for land bridging with planning: 1.06% a month (5 lenders, as at 20 November 2026). Two plain points. First, that product is for land that already has its planning, and just 5 lenders publish a rate for it. Standard bridging is a wider field: 0.76% a month (43 lenders, as at 20 November 2026). Land with an application still pending can price differently, or be offered by fewer lenders again. Second, the figure is a benchmark for the sums, not a quote. On £480,000 that comes to £5,088 of interest a month.
Here is the calendar. The purchase completes in month 0 and the application is validated in month 2. After the decision, allow about three months to sell or refinance. Three possible decision dates follow.
| Month | Cumulative interest | What is happening |
|---|---|---|
| 1 | £5,088 | Site purchased, application being prepared |
| 2 | £10,176 | Application validated |
| 3 | £15,264 | Consultation period |
| 4 | £20,352 | Consultation period |
| 5 | £25,440 | Scenario A: decision on the statutory 13 weeks |
| 6 | £30,528 | Exit work under way |
| 7 | £35,616 | Exit work under way |
| 8 | £40,704 | Scenario A exit. Scenario B: decision after an agreed extension |
| 9 | £45,792 | Exit work under way |
| 10 | £50,880 | Exit work under way |
| 11 | £55,968 | Scenario B exit. Scenario C: late decision |
| 12 | £61,056 | Original 12-month term ends |
| 13 | £66,144 | Extension period |
| 14 | £71,232 | Scenario C exit, two months into an extension |
| 15 | £76,320 | Only if the sale or refinance slips again |
Interest to exit comes to £40,704 in Scenario A, £55,968 in B and £71,232 in C. From A to C, the delay alone costs £30,528 in interest, and only Scenario C runs past the term.
| Fixed costs on the example | Amount |
|---|---|
| Arrangement fee (1% shown) | £4,800. Set by the lender, so ask for the figure early |
| Our fee: 1% of the gross loan, generally due on completion. On a complex case an application fee can apply, agreed in writing first | £4,800 |
| Lender's legal fees | About £1,500 to £2,000 plus VAT on a loan of around £200k; more on a larger loan |
| Your own solicitor | Ask your own solicitor for a quote |
| Valuation | Nil to about £100 for a desktop valuation; up to about £2,000 for a full one, plus VAT |
Planning for the Delay: Four Moves
Price the delay in. Hope is not a plan. Four moves cover most of it.
Match the term to the decision, not to your hopes. In the example, a 12-month loan is fine if the decision comes on time and tight if it does not. Take a longer first term, or get the extension priced at the start, and month 12 can stop being a cliff edge and become a line in the term sheet. Four questions for every lender: is there an extension, how long is it, what does it cost in rate, what does it cost in fee. Find that out while you still have a choice of lender.
Write a plan B exit now. The usual exit is a sale with consent or a refinance. The plan B differs for each site: resubmit a smaller scheme, sell the site as it stands, refinance onto a longer-term loan against the land, or pay the loan down from other assets. We set out at least three or four exits on any deal, and we would rather you chose them in month 0 than month 11.
Stage the money where you can. If part of the loan can be drawn later, for example to cover works after consent, interest runs only on what you have drawn. Whether a lender will do this depends on the deal, so ask. Drawing fewer pounds for fewer months keeps the cost of a delay down.
Use the agreed-time route on purpose. The figures show that most major applications run on a negotiated timetable. If your planning consultant can agree a timetable with the council, put that date, plus a buffer, into the loan term rather than the statutory date.
One more thing to tell us early is a low valuation. The lender lends against the valuer's figure, not what you paid, and a land valuation can depend on the approach taken. One land deal with planning was valued at the £3.3m purchase price and finished past £5m on a different approach and better comparables: what to do when a valuation comes in low. It does not always work, but challenging a low figure is part of the job.
A Few Things People Ask
Does a refusal mean the loan fails?
Can I borrow before planning is decided?
Why does the example use a rate for land with planning?
Is a decision hanging over your site, or are you buying before one? Tell us the site, where the application stands and your plan B.
Indicative terms within 4 hours on straightforward deals, often quicker.
Discuss your deal 0330 223 7872For business or investment purposes only - never secured on a home you or your family live in.
Sources. Ministry of Housing, Communities and Local Government, Planning applications in England: April to June 2026 (gov.uk, updated 29 October 2026). Herbert Smith Freehills Kramer, Planning and Infrastructure Act 2025 in England: update on implementation (17 June 2026). The Planning and Infrastructure Act 2025 (Commencement No. 4 and Transitional Provisions) Regulations 2026, SI 2026/641 (legislation.gov.uk, made 16 June 2026). Burges Salmon, The first draft Environmental Delivery Plan (22 September 2026). Rates: published lender rates, as at 20 November 2026.
Last updated:
More: land without planning · land with planning · development finance · pre-planning land in Cheshire